Monday, 29 February 2016
Roof trusses are in place ready for roof covering before tiling.
Friday, 26 February 2016
Plasterboard is now being installed to the new homes, transforming the interior.
Wednesday, 17 February 2016
The interior fit out is coming on well with the stud walls and electric being fitted in place.
Thursday, 11 February 2016
With the roof trusses now being installed, the first section of roof felt and batten is now going in place.
Friday, 5 February 2016
The roof trusses arrive pre-assembled on a lorry and we can store them in quantities on site.
Monday, 1 February 2016
With the block work now largely finished we are taking delivery of the roof trusses that our crane will lift to the top of the building.