Wednesday, 30 November 2016

This project is now complete and was successfully handed over 18/11/2016. We hope the residents enjoy their new home! 

Monday, 28 November 2016

The project is now nearing completion. These photos show the finished entrance, the main entrance hall and the court yard area with grass and seating areas. 



Friday, 18 November 2016

Photo of one of the finished kitchen areas with fully fitted units, lighting and wooden flooring

Monday, 14 November 2016

Bathroom area now finished and ready for residents with easy accessible shower facility

Monday, 7 November 2016

Work is continuing outside as the patio is laid, plants are planted and benches are installed in the communal garden area.  

Tuesday, 1 November 2016

These CGI's show what the finished Foyer and Cafe areas will look like once the work is complete.  

Saturday, 29 October 2016

Bathrooms are complete with walk in showers for easy and safe  access.  

Monday, 17 October 2016

Finishing touches to the bedrooms have been made ready for residents to move in. 

Tuesday, 11 October 2016

Side view of the main entrance, with work on the front patio nearly complete 

Thursday, 6 October 2016

Monday, 3 October 2016

Living rooms are now fully furnished and ready for residents to move in. 

Saturday, 24 September 2016

All cupboards, fixture and fittings have been installed in the Kitchens 

Monday, 12 September 2016


The coloured glass frames have been installed and it is time to start clearing the tools and equipment from the main entrance   

Friday, 2 September 2016

This view into the courtyard shows the completed exterior of the building. 

Thursday, 1 September 2016

The main entrance is nearing completion as glass panels are installed.  

Thursday, 25 August 2016

Tuesday, 23 August 2016

Monday, 15 August 2016

More progress inside as work continues on the cafĂ©. 

Friday, 12 August 2016

The kitchens are nearly finished and the as the lights are on installed and turned on. 

Wednesday, 3 August 2016

The commercial kitchen is being prepared for installation of cooking equipment

Tuesday, 26 July 2016

The sales suit is being prepared as the toilet is installed, the walls decorated with wallpaper and fixtures and fittings are fitted.   



Tuesday, 19 July 2016

The corridors are nearly ready for flooring and painting. 

Tuesday, 12 July 2016

Progress has been made on the front entrance as the wooden support beams and roofing are installed.  

Tuesday, 5 July 2016

With all the heavy lifting complete the crane has been removed from site

Monday, 4 July 2016

Scaffolding is coming down as work at the entrance lobby progresses

Friday, 1 July 2016

The corridors are starting to take shape as work continues internally

Wednesday, 29 June 2016




The first stages of the new kitchens are being installed




Monday, 27 June 2016

Here’s some of the construction trainees from Weston College who have completed their two week construction trainee programme and secured their CSCS cards. Congratulations! We are delighted to have secured one of the trainees a further four week placement with one of our plastering subcontractors. 

Friday, 24 June 2016

Construction trainees from Weston College in Weston-super-Mare visited Tamar Court to get a taste of life on site.

Wednesday, 8 June 2016

The glass balconies are now being installed, providing outdoor space to those apartments above ground level and bringing more light inside

Friday, 3 June 2016

These are the Gulam beams that sit above the front entrance and are a real feature of the building. The rest of the lobby is taking shape behind the scaffolding






Tuesday, 31 May 2016

The ground floor corridor is plastered and ready for decorating

Tuesday, 24 May 2016

The kitchen in the show apartment in being installed

Friday, 13 May 2016

Up to the 2nd floor, the flats have been boarded and are ready for decorating.

Tuesday, 10 May 2016

The flats on the ground floor have been decorated and are awaiting ‘snagging’ for any finishing touches.

Monday, 9 May 2016

The internal corridor walls have just been boarded and are soon to be decorated.

Friday, 6 May 2016

Outside, the main entrance roof structure is now completed

Tuesday, 26 April 2016

Are you looking to join a rewarding career in the construction industry? 

We’re looking for candidates to take part in a two-week training programme at Weston College followed by the opportunity to get work experience here at Tamar Court’s construction.

To register your interest or for more information call 01934 411594 or email Annie.Keates@weston.ac.uk

Monday, 18 April 2016

Installation of the new kitchens is well underway. 
‘Second fix’ carpentry, including the doors, is now underway.
On to the second floor and the corridor ceilings have now been sealed and boarded.

Monday, 11 April 2016

The internal courtyard roof has now been fully tiled.