Monday, 21 December 2015

Work progressing to the final floor before we start on the roof.

Tuesday, 15 December 2015

Under floor heating being installed and the floor recently screeded.

Friday, 11 December 2015

Another shot of the completed second floor. It has taken longer than expected owing to the high winds we have experienced on site.

Wednesday, 9 December 2015

The next milestone reached as we reach the top of the second floor.

Friday, 6 November 2015

Tuesday, 3 November 2015

We have made good progress over the last few weeks and we are shortly going to install the second floor slabs. 

Monday, 26 October 2015


The communal areas are starting to take shape around the steel frame.

Tuesday, 20 October 2015

Reaching the top of the second floor we are approaching the height of the surrounding buildings.

Friday, 16 October 2015

More materials arriving on site, which will help us reach the top of the second floor and beyond.

Tuesday, 13 October 2015

Work is progressing to the second floor and starting to surround our crane on the site.

Wednesday, 7 October 2015

Two more photos looking at the second floor
going up at Worle Extra Care.

Friday, 2 October 2015

A first look within the interior of the building. This was taken within the ground 

Thursday, 24 September 2015

Brick work to the second floor is now well under way.

Friday, 18 September 2015

Tuesday, 15 September 2015

The first floor has been completed as all the concrete planks are now laid.

Thursday, 10 September 2015

The size of the concrete planks mean it won’t take long to cover over the whole ground floor of the building.
A mobile crane has been brought in to help with the installation of the pre cast concrete planks, which form the base of the first floor.

Tuesday, 1 September 2015

We have hit the next project milestone, having reached the top of the ground floor.

Tuesday, 25 August 2015

More materials arriving on site.
These are our site offices for Rydon staff and our subcontractors working on site.

Thursday, 20 August 2015

Our site hoarding that encloses the site. Soon you will be able to see the building rising above.

Monday, 17 August 2015

The site team is generously donating items to provide to our local food bank on a regular basis.

Friday, 14 August 2015

Welcome to Ebdon Court! More information and news about the project and our site team is displayed on the board just outside our site office
More windows being installed. They will flood lots of natural light in to the building

Thursday, 13 August 2015

Wednesday, 12 August 2015

Our site crane, which lifts a lot of heavy materials around the site and is controlled remotely. 

Thursday, 6 August 2015

Once complete this area will be the new cafĂ© lounge. 
…and this will form part of the new Wellbeing Centre.

Tuesday, 4 August 2015

Protection zones have been established to safeguard a number of existing trees, including this Horse Chestnut.

Friday, 31 July 2015

The first of the window frames are being installed.
The site is getting more busy as work progresses to the first floor and beyond.

Monday, 27 July 2015

Now that the ground work has finished, steel columns are being erected which will provide vital support to the structure. 

Tuesday, 21 July 2015

More blocks arriving on site as we work toward reaching blockwork on the first floor.

Friday, 17 July 2015

The internal scaffolding is now being erected in preparation for work at higher levels.

Tuesday, 14 July 2015


Things are starting to take shape. This is the view of the site with the cement silos right at the back.

Tuesday, 7 July 2015


Some of the team standing on-top of the first successfully installed plank.


Installation of the pre cast concrete ground floor planks has started.

Wednesday, 1 July 2015

We are out of the ground! This photo shows the west elevation of the new building with the first stage of blockwork complete and drainage installed.

Monday, 29 June 2015

The final section of ground beam (foundations) being concreted and made ready for the first stage of blockwork.

Wednesday, 24 June 2015

Tuesday, 23 June 2015

Wednesday, 17 June 2015

North East corner of the building – ground beams constructed awaiting concrete. 
The sub structure blockwork completed awaiting the under floor drainage.


The view from the front of building showing the crane erected in the courtyard.

Wednesday, 10 June 2015

The building is now officially out of the ground, with the first of the pre cast concrete blocks being laid. Pipework for drainage is also being put in place.